22nd October 2010 at 1400hrs Unit 2 at Eraring Power Station was tested at full load capability of 720MW. This unit was performance tested as per contract and passed all performance guarantees. Eraring Energy is satisfied with the performance of the upgraded unit with capacity of 720MW and beyond.