| 1997 |
Established as New World Projects |
| 1997 |
First contract for power station maintenance awarded |
| 1999 |
First major overhaul contract on Unit plant executed (Bayswater turbines) |
| 1999 |
First contract with KPS awarded |
| |
| 2002 |
First Design/Manufacture/Supply project executed (Eraring Unit 3 Ash Hopper) |
| 2004 |
Official Opening of Morisset office and workshop |
| 2005 |
Shell Refinery Turbo-Alternator (TA1) Refurbishment Project awarded |
| 2006 |
Company name changed from New World Projects to Power Projects International |
| 2007 |
Vales Point Boiler Economisers replacement project executed |
| 2007 |
First hydro power plant (Bendeela) overhaul project executed |
| 2007 |
Eraring turbine upgrade contract signed |
| 2008 |
DPPA consortium with Doosan Heavy Industries formally signed |
| 2008 |
Eraring boiler upgrade contract signed |
| |
| 2011 |
Pelican Point gas turbine overhaul project executed |
| 2011 |
Berkeley Vale office and workshop DA approved |
| 2012 |
Completion of Eraring Upgrade Project |
| 2012 |
Construction of Berkeley Vale office and workshop commenced |